3-Week Plan + RAID Log

NHS SBS Healthcare AI Solutions Framework — Submission by 12:00, Tue 7 July 2026

Rebaselined. The Find a Tender notice was amended after first publication: deadline shifted from 23 Jun to 7 Jul. This document supersedes the earlier 4-week and 7-day-sprint versions.

Today: Mon 15 Jun 2026 War-room day 1: Today Last drafting day: Wed 2 Jul 2026 (CEO go/no-go) Internal submit-by: Thu 3 Jul 2026, 14:00 BST Hard backstop: Mon 6 Jul 2026, 14:00 BST Deadline: Tue 7 Jul 2026, 12:00 BST Calendar days available: 22 · Working days available: ~16 Cadence: Tue + Thu 09:30 standup (30 min); CEO Wed + Fri 16:00 check-in (30 min) War-room owner: Fractional COO

Burn rate

Each working day = ~6% of total bid capacity. The 22-day window absorbs single-day slippage cleanly; absorbs a 2-day slip if compensated by weekend work. Anything beyond 3 days slipped without recovery puts the red-team window at risk.


A. Role assignments (confirmed this week)

RoleOwnerTime commitmentStatus
SRO / final sign-offBritiAI CEOWed + Fri check-ins + final sign-off Wed 2 JulConfirmed
Bid DirectorFractional COOFull-time, 3 weeksLive
Bid Manager (Ariba upload, version control)External contractorFull-time from Wed 17 JunEngage by Tue 16 Jun
Technical Author / Solution ArchitectCTO (Jacky) + Votee Chief Scientist60–80%Confirmed (per CTO WhatsApp)
Research / Evidence LeadBeever lead30%Confirm Tue 16 Jun
Clinical Safety Officer (DCB0129)Contract appointment5 daysEngage by Fri 20 Jun
Information GovernanceInternal or contractor40%Identify Tue 16 Jun
Cyber / ISO 27001 Stage 1 + CE+External consultant3 daysEngage Tue 16 Jun; CE+ assessment booked w/c 23 Jun
Legal (Teaming Agreement + framework T&Cs)External3 daysBrief Tue 16 Jun
Commercial / PricingBritiAI CFO + COO25%Live
Reference / case studiesSales + Marketing20%Live

B. Week-by-week plan

Week 1: Mon 15 – Sun 21 Jun — Mobilise, contract, decide

Theme: secure all external contracts, sign HoT with Votee + Beever, complete capability/gap analysis, kick off compliance and CSO engagement.

DayTaskOwnerOutput
Mon 15CEO confirms GO; budget unlocked; submission_tracker liveCEO + COODecision log; tracker shared
Mon 15Ariba RFx 1110014540 access confirmed; ITT pack downloadedCOO / Bid MgrITT artefacts on shared drive
Mon 15First informal clarification email to NHS SBS mailbox (enquiry deadline passed)COOEmail sent
Tue 16Bid Manager contracted; SoW signedCOOContract executed
Tue 16Clinical Safety Officer providers contacted (3 in parallel: Clinical Safety Ltd, Hempsons, Salus)COO3 SoWs returned
Tue 16Cyber/IG consultant engaged for CE+ + ISO 27001 Stage 1 narrativeCOOSoW signed
Tue 16Legal briefed; Heads of Terms draft issued to Votee + BeeverLegal + CEOHoT issued
Wed 17DSPT registered; “Approaching Standards” path agreedIGRegistration evidence
Wed 17Capability vs ITT gap analysis — confirm lot scope (5 + 6 + 7 primary)CTO + COOScope decision logged
Wed 17Skeleton response structure built in AribaBid MgrAll fields stubbed
Thu 18DTAC v2 gap analysis kick-offIG + CSOGap list + plan
Thu 18Trust reference letter outreach starts — top 10 listSales≥5 conversations booked
Fri 19CSO contract signed; named individual confirmed (item 19 closed)COOEngagement letter
Fri 19Heads of Terms signed by Votee + BeeverCEOHoT executed
Fri 19CEO Wed/Fri check-in #1 — verify all week 1 contracts in placeCEO + COOSign-off
Sat 20 / Sun 21Optional: bid writer drafts qualification section narrativesBid MgrSection drafts

Week 1 exit criteria:

  • CEO GO + budget unlocked
  • Ariba access + ITT downloaded
  • Bid Manager + CSO + Cyber consultant + Legal all contracted
  • HoT signed by Votee + Beever
  • DTAC gap analysis complete
  • DSPT registered
  • Lot scope confirmed (5 + 6 + 7 primary; 3 + 4 stretch)

Week 2: Mon 22 – Sun 28 Jun — Build, draft, evidence

Theme: produce v1 of every quality response, generate solution architectures + safety case skeletons, finalise pricing, complete Teaming Agreement.

DayTaskOwnerOutput
Mon 22Technical compliance matrix vs ITT mandatoriesCTOMatrix complete
Mon 22Solution architecture diagrams kick-off (1-pager × 4–6 named solutions)CTO + VoteeDrafts
Tue 23CE+ assessment dayCyber leadPass certificate or path-to-pass
Tue 23Quality response v1 — Lot 6 (Operational Efficiency — 90% quality)CTO + COODraft v1
Wed 24Per-lot go/no-go gate on stretch lots 3 + 4AllDecision logged
Wed 24Quality response v1 — Lot 7 (Advisory)COODraft v1
Wed 24Pricing model locked — Lot 7 rate card sharpened (20% commercial weight)CFO + COOPricing pack signed
Wed 24CEO check-in #2CEO + COOSign-off
Thu 25Quality response v1 — Lot 5 (Research)Beever + COODraft v1
Thu 25Solution architecture diagrams completeCTOAll diagrams
Fri 26DCB0129 CSMS statement + CSC skeleton + Hazard Log per solutionCSO + CTOSafety pack v1
Fri 26Social Value Plan v1 (10% of every lot — scored response, not boilerplate)COOSVP v1
Fri 26Full Teaming Agreement signed (Votee + Beever)CEO + LegalSigned TA
Fri 26Case study assembly: 3 BritiAI + 2 Votee + 1 Beever; per-lot mappingSalesCase study pack
Fri 26NHS reference letter — first commitment securedSales1 letter committed
Fri 26CEO check-in #3 — readiness for red-teamCEO + COOSign-off
Sat 27 / Sun 28Buffer; weekend rate available if needed

Week 2 exit criteria:

  • v1 drafts complete on all primary lots (5, 6, 7) and any retained stretch lots
  • Solution architectures + safety case skeletons in place
  • Teaming Agreement signed
  • CE+ assessment passed or evidenced path-to-pass
  • Social Value Plan v1 drafted
  • At least 1 NHS reference letter committed verbally

Week 3: Mon 29 Jun – Sun 5 Jul — Red-team, polish, evidence lock

Theme: external challenge, rewrites, final sign-offs, evidence assembly into Ariba.

DayTaskOwnerOutput
Mon 29Internal red-team prep — read-through packBid MgrIssues log
Tue 30External red-team review (full day; independent bid consultant)ExternalScored review + actions
Tue 30DCB0129 Clinical Safety Case finalisedCSOCSC signed off
Wed 1 JulRewrites — Lot 6 to draft v2CTO + COODraft v2
Wed 1 JulRewrites — Lot 7 to draft v2COODraft v2
Wed 1 JulCEO check-in #4CEO + COOSign-off
Thu 2 JulRewrites — Lot 5 to draft v2Beever + COODraft v2
Thu 2 JulWin-theme audit: every section threads the 5 win themesBid MgrAudit log closed
Thu 2 JulLegal review of all commercial commitmentsLegalSign-off
Thu 2 JulNHS reference letter receivedSalesLetter in evidence pack
Thu 2 JulCEO final go/no-go per lotCEOLot-by-lot sign-off
Fri 3 Jul morningFinal pack compile into Ariba formsBid MgrPack complete
Fri 3 Jul 11:00Final dry-run in Ariba previewBid MgrAll fields validated
Fri 3 Jul 14:00SUBMIT — 96 hours before deadlineBid MgrSubmission confirmation captured
Fri 3 Jul 15:00Team retro + thank-yousAll
Sat 4 – Sun 5 JulQuiet

Backstop window: Mon 6 Jul 09:00–14:00 — only used if Fri submission failed Hard deadline: Tue 7 Jul 12:00

Week 3 exit criteria:

  • Red-team complete + actions closed
  • v2 drafts on all in-scope lots, signed off by CEO
  • CSC + Hazard Log finalised
  • All evidence attached in Ariba
  • Pack submitted ≥96 hours before deadline

C. RAID Log — REVISED for 22-day plan

Risks

IDRiskLIScoreOwnerMitigationContingency
R1ISO 27001 not certified; CE+ pending4312Cyber leadCE+ assessment w/c 23 Jun, target pass by 4 Jul; ISO 27001 Stage 1 documentation review; declare both with CEO-signed roadmapLower score on IG question; offset with DSPT + Votee controls reference
R2DCB0129 CSO not engaged by Fri 20 Jun2510COOThree parallel calls Tue 16 Jun; standard 5-10 day engagement; CEO contracting authority pre-clearedUse Votee in-house safety practitioner under named CSO supervision
R3Lot 5 v1 draft insufficient by Thu 25 Jun339Beever + COOWed 24 Jun gate; if v1 not forming, drop and submit Lots 6 + 7 onlyConfirmed acceptable fallback
R4Votee/Beever Teaming Agreement signature slips past Fri 26 Jun2510Legal + CEOHoT signed Fri 19 Jun; full TA template ready Mon 22 JunVerbal HoT + side letter as bridging while TA finalised
R5Data sovereignty objection (Votee HK HQ)3412CTOUK-only deployment topology (already drafted — item 24); UK sub-processor list; binding DPA flow-down in TAWritten undertaking from Votee leadership re: data flows
R6Bandwidth — CTO 80% + COO full-time over 3 weeks339COOTue/Thu standups; Wed/Fri CEO check-ins prevent drift; weekend rate availableDrop stretch lots first, keep Lots 6 + 7 clean
R7Ariba portal technical failure on submit day2510Bid MgrSubmit Fri 3 Jul 14:00 (96h buffer); backups in two locations; screenshot every stepEmail NHS SBS mailbox pre-deadline with evidence of attempt; use 6 Jul backstop window
R8NHS reference letter not received by 2 Jul428SalesApproach 10 trusts; target 1 verbal commitment by Fri 26 Jun, letter by Thu 2 JulSubmit without; lean on Votee academic + Beever ACL + BritiAI horizontal
R9Financial threshold not met by BritiAI alone3412CFOAggregate via consortium financials; parent guarantee if available; group accountsLimit bid to lots with lower turnover requirement
R10Clarification answer from NHS SBS arrives late / changes scope248COOInformal mailbox channel only — enquiry deadline passed; build narrative tolerant to either answerRe-baseline within 24h of any material change
R11Social Value Plan under-scored (10% of every lot)3412COOUpgrade to fully scored response by Fri 26 Jun; PPN 06/20 alignment with measurable commitmentsLose ~3% of total scored quality — accept if Lot 6 narrative dominates
R12Overclaim risk → fails as MHRA-class device155CSO + LegalStrict bid-language review by CSO Tue 30 JunWithdraw any solution that crosses line

Assumptions (validate this week via informal NHS SBS contact + Ariba ITT pack)

IDAssumptionValidate by
A1The 8-lot structure as published is finalMon 15 Jun (ITT download)
A2Direct award permitted from framework go-live (26 May 2027)Informal Q to NHS SBS
A3Aggregated consortium financials are acceptable for selectionInformal Q + ITT pack review
A4Reference projects can be non-NHS if NHS-comparable in scale + governanceInformal Q
A5ISO 27001 “in flight with roadmap” is acceptable (not pass/fail disqualifying)Informal Q + ITT pack review
A6Lot 8 enrolment is automatic (per notice §Lot 8) and does not need a separate quality narrativeConfirmed by notice; verify against full ITT pack
A7”Tenders may be submitted electronically: No” is a notice anomaly — Ariba upload is the legally valid routeInformal Q

Issues

IDIssueOwnerAction
I1Enquiry deadline (12 Jun) passed — formal clarification route closedCOOInformal email channel to nsbs.procurementsolutionssourcing
I2No NHS-branded case study material exists todaySalesReference letter campaign — target 1 by 2 Jul
I3BritiAI website lacks NHS positioningMarketingDefer until post-submission

Dependencies

IDDependencyOn whomLatest date
D1Signed Heads of TermsVotee + Beever leadershipFri 19 Jun
D2Signed full Teaming AgreementLegal + Votee + BeeverFri 26 Jun
D3CE+ certificate or evidenced passExternal assessorFri 4 Jul
D4DTAC v2 evidence packIG + CSOFri 26 Jun
D5CSO engagement signedContract CSOFri 20 Jun
D6Pricing sign-offCFOWed 24 Jun
D7CEO final go/no-go per lotCEOThu 2 Jul
D8NHS reference letter (1)Trust contactThu 2 Jul

D. Budget envelope — revised for 3-week structured plan

LineCost (£)
External Bid Manager (3 weeks FT)18,000
Bid writer support5,000
Clinical Safety Officer contract (standard rate, 5 days)6,500
Cyber Essentials Plus assessment3,500
ISO 27001 Stage 1 documentation consultancy7,500
Legal — Teaming Agreement + framework T&Cs review7,000
Insurance uplift if required3,500
Red-team external review4,500
Trust reference letter outreach (incidentals)1,500
Internal time (BritiAI + Votee + Beever, notional)25,000
Contingency (15%)11,500
Total cash + notional~£93,500
Cash only~£68,500

Cash budget restored to ~£68k (vs the £50k 7-day-sprint version) because we are now buying proper compliance assessment rather than skipping it.


E. Communication plan

  • Internal: Tue + Thu 09:30 standups (30 min); shared Slack/WhatsApp #nhs-sbs-bid; shared Drive /NHS_SBS_Bid
  • Votee + Beever: Mon + Thu 16:00 sync (45 min)
  • CEO: Wed + Fri 16:00 check-in (30 min)
  • Board / investors: Friday email update from CEO
  • External (trusts): Sales-led outreach; messaging templates pre-approved by COO; target 1 reference letter by Thu 2 Jul

F. Single-page decision summary (CEO sign now if not already)

Decision required: GO / NO-GO confirmation on submitting a bid for NHS SBS Healthcare AI Solutions Framework SBS10523 by 12:00 Tue 7 Jul 2026.

Recommended scope: Lots 5, 6, 7 as primary. Lots 3, 4 as stretch (decided Wed 24 Jun). Lot 8 automatic.

Recommended structure: BritiAI prime; Votee + Beever named subs via Teaming Agreement.

Budget required: ~£68k cash, ~£94k total inc notional internal time.

Top three risks: (1) ISO 27001 + CE+ partial — declare with roadmap; (2) CSO contract not signed by Fri 20 Jun — three parallel providers contacted Tue 16 Jun; (3) Social Value Plan under-scored — upgrade to fully scored response by Fri 26 Jun.

If we say no: locked out of the primary NHS AI procurement route until ~2030 re-opening. Sovereign AI Fund equity pitch loses its strongest anchor-customer story.

Signature: ____________________ Date: ___ Jun 2026