NHS SBS Healthcare AI Solutions Framework — Master Index
📅 Deadline: Tue 7 Jul 2026, 12:00 BST · Internal submit-by: Fri 3 Jul 14:00 📝 Reference: SBS10523 · Portal: SAP Ariba RFx 1110014540 👥 Bid director: Fractional COO (Tich) · SRO: CEO (Wadii) · Technical lead: CTO (Jacky, Votee)
Daily entry points
- NHS Procurement Bid Tracker — live status of all 36 submission artefacts
- 02_Execution_Plan_RAID — 3-week plan + RAID
Strategic docs
- 01_Strategic_Plan — bid strategy, scope, decisions
- 03_Proposal_Narrative_Draft — drafted prose for Lots 5, 6, 7
- 04_Team_Briefing_Deck — slide outline for team session
- 09_BritiAI_ITT_Mapping — official notice mapped against our position
Deliverables (swarm output)
deliverables/
├─ 01_BidMgr/ Bid Management Plan, Ariba response map, version control SOP, evidence index, submit-day runbook
├─ 02_BidWriter/ Polished Lot 5/6/7 narratives + Executive Summary
├─ 03_CSO/ DCB0129 CSMS, Clinical Safety Case Reports, Hazard Log, DCB0160 engagement
├─ 04_CEPlus/ CE+ readiness, gap analysis, remediation, controls register
├─ 05_ISO27001/ ISMS scope, SoA, gap analysis, risk register, policy framework, certification roadmap
├─ 07_RedTeam/ Independent red-team findings report
├─ 09_TrustOutreach/ Trust dossiers, email templates, LinkedIn scripts, reference letter templates
Dashboard
- Local:
dashboard/index.html— open in browser - Excel:
dashboard/excel/submission_tracker.csv(or runbuild_xlsx.pyfor styled .xlsx) - Web:
dashboard/web_deploy/— deploy to Cloudflare Pages + Access (see DEPLOYMENT.md) - Cron:
dashboard/cron/daily_redteam_update.sh— daily digest to red-team list
Live status (refreshed at standups Tue + Thu 09:30)
| ⏱ Days remaining | 22 calendar / ~16 working |
| ✅ Done | 3 |
| 🟢 Drafted | 10 |
| 🟡 Partial | 9 (incl. CSO — identified, contracting) |
| 🔴 Not started | 12 |
| ⛔ Gating | 0 (was 1 — CSO crisis cleared) |
| N/A | 1 (Lot 8 automatic) |
| In-flight or better | 63% |
Critical updates today
- Deadline amended 23 Jun → 7 Jul. 22 days, not 8.
- Votee + Beever ISO 9001 certified — used as partner QMS evidence.
- ISO 27001 in progress at Votee/Beever — declared with dated roadmap.
- CSO identified — contracting in process. Gating risk cleared.
- Lot 8 automatic on ≥2 lot wins — no separate bid needed.
- Lot 6 award criteria: Q 90% / SV 10%, no cost — pure quality race.
- Basic CE-now strategy adopted (per Votee assessment §1.2) — separates from CE+.
Gantt — 3-week plan
gantt title NHS SBS bid · Mon 15 Jun → Tue 7 Jul 2026 dateFormat YYYY-MM-DD axisFormat %d %b section Week 1 · Mobilise Bid Mgr + CSO + Cyber contracted :crit, w1a, 2026-06-16, 4d Basic CE certification :w1b, 2026-06-17, 3d Heads of Terms (Votee/Beever) :crit, w1c, 2026-06-17, 3d DTAC v2 gap analysis :w1d, 2026-06-18, 9d DSPT registration :w1e, 2026-06-17, 1d section Week 2 · Build CE+ assessment :w2a, 2026-06-23, 4d Lot 5/6/7 quality drafts v1 :crit, w2b, 2026-06-23, 4d Solution architecture diagrams :w2c, 2026-06-22, 4d Pricing locked :milestone, 2026-06-24, 0d Stretch-lot go/no-go (3 + 4) :milestone, 2026-06-24, 0d Social Value Plan upgrade :w2d, 2026-06-22, 5d Teaming Agreement signed :crit, 2026-06-26, 1d section Week 3 · Submit Red-team review (external) :crit, w3a, 2026-06-30, 1d v2 rewrites :w3b, 2026-07-01, 2d CEO go/no-go per lot :milestone, 2026-07-02, 0d Pack compile + Ariba load :w3c, 2026-07-03, 1d SUBMIT (96h before deadline) :crit, milestone, 2026-07-03, 0d Backstop window :w3d, 2026-07-06, 1d DEADLINE :crit, milestone, 2026-07-07, 0d
Note: the Mermaid Gantt above renders natively in Obsidian. In a regular markdown viewer, install a Mermaid plug-in or open
dashboard/index.htmlfor the interactive Gantt.
Tags taxonomy (for Obsidian search)
#nhs-sbs— anything about this framework#lot/5,#lot/6,#lot/7,#lot/8— lot-specific#compliance/ce,#compliance/iso27001,#compliance/iso9001,#compliance/dspt,#compliance/dtac,#compliance/dcb0129— compliance threads#partner/votee,#partner/beever— partner-specific decisions#risk— RAID risks#decision— board-level decisions#commercial,#pricing,#social-value— commercial threads#draft,#approved,#submitted— artefact state#red-team— red-team findings + responses
Wiki-link convention
- Files use spaces in filenames so Obsidian wiki-links read naturally:
[[NHS Procurement Bid Tracker]] - Numbered files (
01_…,02_…) keep their numeric prefix so Finder + Obsidian both sort sensibly - All deliverables in
deliverables/NN_<Theme>/are referenced relative to repo root, not via wiki-link